East Campus Update

East Campus:

May 2017 - Construction completed.

 

February 13, 2017 - Conditional Certificate of Occupancy was received for the site; garage; and Congressional, Federal, and Constitution Halls.

Surface parking lot, underground garage, and loading area are operational now.

The new Nebraska Avenue pedestrian crossing signals have been installed and are operational.

Interior work on Don Myers Technology and Innovation building is 90 percent complete.

Interior work on Congressional, Federal, and Constitution Halls are 99 percent complete.

November 14, 2016 - Site utilities (water and sewer) installation is complete.

Nebraska Avenue pedestrian crossing signal installation is complete.

Installation of precast and exterior envelope for Buildings 2 and 3 is complete, and nearing completion on Building 1.

Permanent power connection is complete.

South and north plaza work nears completion with installation of landscaping, fencing, and site lighting.

Buildings 2 and 3 interiors near completion, with “punch list” under way.

August 3, 2016 - Infrastructure for new Nebraska Avenue pedestrian crossing signal is complete, and installation is under way.  

Lightweight concrete pour for Technology and Innovation Building is complete. Concrete pours for site continues.  

Plaza work is under way with geofoam backfill, site utilities, and planter walls. Sidewalks are nearly completed.  

All tower cranes and concrete batch plant have been removed from site, and precast crane will be dismantled in early August.

Building footings, foundation walls, and exterior walls are complete. Window installation is approximately 75 percent complete while roofing continues.

Permanent foundation water proofing is nearly complete.

Garage Parking P1 and PT levels concrete pour is complete, MEP (plumbing, ductwork, lighting, power) is nearly complete, and concrete stairs and masonry walls have been installed.

Parking and PT slab are on grade and service/loading area has been installed.

All building structural walls and floors are complete.

Residence 1, 2, and 3 precast and roofing are complete. Window installation is nearly complete.

Noise and vibration monitoring, dust control, and site cleaning measures continue.

May 13, 2016 - Building excavation is complete.

Nebraska Avenue pedestrian crossing signal installation set to begin in June.

Noise and vibration monitoring, dust control, and site cleaning measures are ongoing.

Plaza work commenced with installation of geofoam backfill, site utilities, planter walls, and sidewalks.

Installation of building footings and foundation walls are complete.

Water proofing of permanent foundation is 95 percent complete.
 
Concrete pour for Parking P1 level is complete. MEP (plumbing, ductwork, lighting, power) is 95 percent complete. Concrete stairs and masonry walls have been installed.

Concrete pour for Parking PT level is complete. MEP (plumbing, ductwork, lighting, power) is nearly complete. Concrete stairs and masonry walls have been installed.

Parking and PT slab on grade and service/loading area has been installed.

All building structural walls and floors are complete.
 
Precast and roofing for Residence Halls 2 and 3 are complete, and installation of windows is 90 percent complete. Precast for Residence Hall 1 is 30 percent complete.

A second crane for precast erection is expected to arrive in late May for the south side of Building 1.

February 10, 2016 - Building and site utilities excavation on New Mexico Avenue are both complete.

Weekly sampling for testing and dewatering by DC Water is ongoing  

Tower crane 2 (nearest New Mexico Avenue) has been removed.

Footings and foundation walls are complete.

Permanent foundation water proofing is ongoing.
 
Parking P1 level concrete pour is complete, as work on plumbing, ducts, and lighting is in progress.  

Parking PT level garage concrete pour is complete, as work on plumbing, ducts, and lighting is in progress.  

Installation of parking and PT slabs on grade and service/loading area is complete.

Installation of plaza and first-floor slabs for buildings 2, 3, and Technology & Innovation building is complete.

Crane for precast erection is expected to arrive the week of February 8.

November 10, 2015 - Building excavation is complete.

Noise and vibration monitoring, dust control, and site cleaning measures are ongoing.

New approved work hours of 7 a.m. to 7 p.m., Monday through Friday, and 8 a.m. to 4 p.m., Saturdays are being followed.

Footings and foundation walls are 98 percent complete.

Permanent foundation water proofing is under way. 

The concrete pour on parking garage levels P1 and PT is complete, and concrete stairs and masonry walls are being installed.  

Plaza slab and first-floor slabs for buildings 2 and 3 are 80 percent complete.

September 17, 2015 - Installation of sheeting piles and wood lagging is complete.

Mass earth excavation is complete, with minor excavation still under way for footings.  

Geopier foundation system production piles are complete.

The two tower cranes continue to pour concrete from the batch plant. 

Concrete footings and foundation walls are 70 percent complete.

Waterproofing of permanent foundation continues.

Parking P1 level concrete pour is complete, and installation of stairs and walls is under way.

June 11, 2015 - Sheeting piles and wood lagging work is complete.

Installation of Geopiers is approximately 85 percent complete. 

Excavation for underground garage is approximately 95 percent complete.

Noise and vibration monitoring, dust control, and site cleaning measures are ongoing.

Pepco has installed temporary power for work site.

Installation of concrete batch plant is complete.

Two tower cranes have been erected and are operational.

Work on concrete footings and foundation walls has begun.

April 10, 2015 - Sheeting piles and wood lagging are complete for excavation.

Geopier foundation system production piles process is under way and approximately 25 percent complete (1,500 total piers).

Mass earth excavation for underground garage is approximately 75 percent complete.

Noise and vibration monitoring, dust control and site cleaning measures are under way. 

Temporary Pepco power installation nears completion.

Below grade concrete pour is expected to begin in April.

Tower crane installation is scheduled for April.

March 2, 2015 - Installation of dewatering well and sediment tanks is complete.

Piping is connected to drain, and dewatering pumping is ongoing.

Geopier foundation system test piles are scheduled for week of March 2.

Groundwater sampling for testing and dewatering is ongoing, as tests will be performed on a monthly basis.

Excavation is approximately 70 percent complete.

Temporary Pepco power design has been approved for construction, and installation is expected to begin in March.

January 6, 2015 - Installation of sheeting piles and wood lagging are complete.

Installation of dewatering well and sediment tank are complete.

Initial groundwater sampling for testing and dewatering is complete. Additional sampling and testing will be performed on a weekly and monthly basis. 

Excavation is approximately 60 percent complete.

Vibration and noise monitoring as well as dust control and site cleaning measures remain ongoing.

December 5, 2014 - Erosion and sediment controls are in place and being maintained.

Sheeting piles are complete;wood lagging installation along south, east, and west sides of site near completion.

Dewatering well installation is complete;sediment tanks are on site;piping is completed to drain;and pumping to commence shortly.

Initial groundwater sampling for testing and dewatering to begin week of Dec. 8.

Excavation is under way.

October 30, 2014 - Erosion and sediment control measures are in place and are being maintained.

Sheeting piles are complete, and installation of wood lagging is under way along south, east and west sides of site.

Installation of dewatering well is complete.

Sediment tanks are on site now. 

Piping work is nearing completion for connection to drain, as excavation proceeds.

October 2, 2014 - Erosion and sediment control installation is complete and approved (silt fences, inlet protection, etc.).

Driving and sheeting of piles is complete. Tie backs are expected to begin next week, as excavation progresses.

Dewatering well installation is nearing completion. Wells are expected to be completed, and dewatering is set to begin in approximately two weeks.

Mass excavation and hauling of soil off-site is expected to begin on October 2 along the approved routes.

August 29, 2014

  • Week of September 1, 2014 Sheeting and shoring piles delivered to the site. On-site beam fabrication/preparation.
  • Week of September 8, 2014 Dewatering well installation scheduled to begin. Pile driving scheduled to begin.
Mass excavation of the site is scheduled to begin the week of October 13.

May 15, 2014 - Skanska, the project development construction group, will begin to secure the Nebraska Ave. parking lot (future East Campus site) beginning on Monday, May 19.

Skanska will install fencing, and also will connect to the site's existing power and water services for their temporary needs.

Facilities Management will remove containers and any loose items on the New Mexico Ave. parking lot during the week of May 19.

For public safety, emergency telephones and existing site lighting will remain operational until fence installation is complete.