Past Updates
May 9, 2013 - Concrete floor leveling and toping installation is under way.
Installation of interior wall, duct work, electrical work, and sprinkler systems continues.
First floor drywall installation is complete. Second floor drywall installation is expected to be completed this week.
Work on the sanitary line continues.
Exterior masonry work continues.
Chilled water line connection from Katzen is near completion. Roofing installation is 95 percent complete.
Boiler shut down and heating system interconnections to Katzen are scheduled for early June.
Tree removal permits for trees in the public space affected by the water line construction are being coordinated with AU Grounds Operations and the appropriate District governmental agencies.
April 5, 2013 - Interior wall, duct work, electrical work and sprinkler systems installation continues.
Work on the sewer line is expected to begin this week.
First layer of exterior sheeting is complete.
Roofing installation continues.
Installation of the parapet wall is under way.
Sewer line work continues.
March 22, 2013 - Interior wall, duct work, electrical work, and sprinkler systems installation continues.
Exterior siding work is under way.
Terrace level concrete pour is complete.
Roof planking placement is complete. Materials are expected to arrive this week to begin roof installation, weather permitting.
Katzen chilled water interconnection/outage work is scheduled for March 22 – 23.
March 14, 2013 - Interior wall, duct, and sprinkler systems installation continues.
Roof planking placement is expected to be completed this week.
Roofing materials are scheduled to arrive this week and roofing installation will begin, weather permitting.
March 7, 2013 - Interior wall, duct, and sprinkler systems installation continues.
Roof planking is complete with exception of four panels that will be place once structural re-shoring is complete. Roof material installation is expected to begin next week.
Interconnection of the chilled water system currently is expected to begin on March 22.
February 28, 2013 - Third-floor planking installation and metal framing is complete.
Roof plank installation is expected to begin at the end of this week.
February 25, 2013 - Construction on the first and second floors and wall sections are complete.
Installation of underground heating and cooling piping between Nebraska and Katzen is complete.
Cleaning and re-grading of the area behind Katzen is under way, and is expected to be completed by March 8, weather permitting.
Improvement on access through 44th Street gate, including reconstruction of the sidewalk, is scheduled for the week of February 25, weather permitting.
Construction of the 44th Street storm water structure installation is under way.Saturday work continues as approved.
Third floor wall sections construction is under way.
Roof deck installation is expected to begin on February 28.
Planning for installation of new domestic water and sanitary sewer connections from Nebraska Ave. continues.
New landscaping for construction-affected area behind Katzen is scheduled for late spring.
February 20, 2013 - Third floor planking installation continues. Wall framing and duct work will follow soon thereafter.
All foundation work is complete.
Pouring for the terrace level concrete slab is planned for Thursday, February 21.
Mechanical connection work continues between Nebraska Hall and the new addition.
February 13, 2013 - Third floor plank is expected to be installed this Friday.
Second floor wall framing and ductwork installation is in progress.
All under-slab work is complete.
Pouring for the terrace level concrete slab is planned for Thursday, February 21.
Mechanical connection work continues between Nebraska Hall and the new addition.
February 6, 2013 - Second floor planks are being installed this week.
All under-slab piping, conduit placement work is complete and gravel infill is being finalized in preparation for the pouring of the concrete floor.
January 30, 2013 - Second floor planks are expected to be installed later this week, and completed by next week.
Installation of heating and cooling piping for the interconnection with the Katzen Arts Center continues, and is expected to be completed in early February. Site restoration will begin shortly thereafter, including the replacement of the interconnecting sidewalk between the 44th street pedestrian gate and Katzen Arts Center.
Gravel continues to be placed on the terrace level with the pouring of the concrete floor scheduled for early February.
January 24, 2013 - First floor precast flooring is complete, and first floor wall framing is under way.
Installation of heating and cooling piping for the interconnection with the Katzen Arts Center continues and is expected to be completed by the end of the month. Site restoration will begin shortly thereafter, including the replacement of the interconnecting sidewalk between the 44th street pedestrian gate and Katzen Arts Center.
Construction of the storm water receiver work on 44th street is under way.
Interior heating and cooling piping changes are under way.
Electrical and mechanical work for the terrace level continues.
January 16, 2013 - Installation of heating and cooling piping for the interconnection with the Katzen Arts Center continues, and is expected to be completed by the end of January. Construction of the storm water receiver on 44th street also is under way.
Restoration of the interconnecting sidewalk between the 44th street pedestrian gate and Katzen Arts Center will begin shortly thereafter.
First-floor hollow plank flooring will be installed this week.
Underground plumbing and electrical work continues.
January 9, 2013 - Installation of heating and cooling piping for the interconnection with the Katzen Arts Center continues, and is expected to be completed by the end of the month. Site restoration will begin shortly thereafter, including the replacement of the interconnecting sidewalk between the 44th street pedestrian gate and Katzen Arts Center.
Underground plumbing and electrical work continues.
Construction of the storm water receiver on 44th street is under way.
December 19, 2012 - Construction of the telecommunication data room is complete.
Preparations for the elevator shaft are complete.
Installation of water piping for the interconnection with the Katzen Arts Center continues, and is expected to be completed by the end of the month.
Restoration of the construction site will begin shortly thereafter, including the replacement of the interconnecting sidewalk between the 44th street pedestrian gate and Katzen Arts Center.
Underground plumbing and electrical work continues.
December 12, 2012 - First floor wall construction continues.
Installation of water interconnection with the Katzen Arts Center continues, and is expected to be completed by the end of this month.
Nebraska Ave water interconnection work has begun and will continue during the winter break.
Under-slab plumbing and electrical work continues.
December 5, 2012 - Construction of the first floor and terrace level telecommunications data room walls are under way.
This week, the last concrete grade beams were poured; new terrace wall pours will be completed; and under-slab plumbing and electrical work is under way.
To make room for the new electrical equipment, relocation of the telecommunication point of presence in the lower level of the existing building has been scheduled.
November 28, 2012 - The first floor walls are under construction.
Concrete grade beam work continues.
Installation of hydronic piping for the interconnection with the Katzen Arts Center continues, and is expected to be completed in early December.
Site restoration is expected to begin shortly thereafter, including the replacement of the interconnecting sidewalk between the 44th street pedestrian gate and Katzen Arts Center.
November 16, 2012 - First floor walls are under construction.
Concrete grade beams work continues.
November 7, 2012 - First floor wall sections have begun to be installed.
Grade beams continue to be poured, with the majority having been completed. Concrete base floor will be poured a soon as the grade beams have been completed.
Installation of heating and cooling piping for the interconnection with the Katzen Arts Center has begun and is expected to continue for the next two weeks.
Telecommunication equipment in the lower level of the existing building is scheduled to be relocated to make room for new electrical equipment.
A meeting was held with representatives of the Ft. Gaines Citizen's Association to discuss ongoing communication between AU's project team and the Association. A proposal was made for a construction bulletin to be issued bi-weekly by AU to the Association that would highlight current activities and identify dates when noise or other site activities may affect the neighborhood.
October 24, 2012 - Remaining installation of grade beams continues. Grade beams adjacent to the northeast corner of the existing building are being reinforced with additional underpinning, and are expected to be completed shortly.
Pouring of the first floor vertical walls and slab is under way.
Utility location and coordination is underway. Interconnections to the Katzen Center also are being installed.
October 19, 2012 - Additional underpinning to reinforce the grade beams adjacent to the northeast corner of the existing building is expected to be completed next week.
October 10, 2012 - Installation of the foundation grade beams continues, and is expected to be completed in the next week.
October 3, 2012 - Installation of the foundation grade beams continues.
Structural accommodations have been made to the existing building in preparation for elevator pit construction.
September 27, 2012 - Foundation piles are complete.Installation of the foundation grade beams has begun.
September 19, 2012 - Site excavation continues.
September 11, 2012 - Site excavation is almost complete with only a concrete foundation left to excavate.
Installation of foundation pile is expected to continue through next week and completed by September 19.
Construction of the concrete grade beam is expected to begin on September 13.
September 5, 2012 - Foundation pile installation continues, and is expected to be completed by Friday, Sept. 7.
Electrical and mechanical work connecting the existing Nebraska Hall to the new extension began on Wednesday, Sept. 5.
August 15, 2012 - Site excavation continues.
August 8, 2012 - Site excavation continues with the removal of the concrete and asphalt driveway and parking area.
Drilling and foundation construction will begin next week.
August 1, 2012 - The temporary access road has been completed and site excavation has begun with the removal of concrete and asphalt driveway and parking area.
July 24, 2012 -Work on site began on Monday, July 23.
Construction of temporary entrance road will begin this week.
Drill rig will be brought on site Thursday, July 26 to begin work on foundation pile.
The webcam has been installed on the site, and work progress can be viewed on the Media Gallery Page.
July 19, 2012 - Permits for the removal of “special” trees are being secured currently.
Work has begun on the relocation of the electrical generator to the other side of the building. Related miscellaneous electrical work is expected to take place during the remainder of this week.
Construction to entrance road will begin this week.
July 12, 2012 - Storm damage was minimal within the construction zone.
Work on the entrance road to the site is expected to begin later this week.
May 16, 2012 - The Nebraska Hall parking lot is now closed due to construction. A construction fence will be erected in the next several days. Parking is available in the Nebraska Avenue commuter parking lot or the Katzen Arts Center parking garage.
May 15, 2012 – Demolition and site preparation work on the three-story addition to be built on Nebraska Hall is scheduled to begin in mid-May.