(UA) – Jerry Gager
School of International Service (SIS):
Excavation is proceeding. The current position
is about ten feet from the bottom of the planned
excavation. Pile driving is about 75% complete
and is expected to be finished by mid June. The
footing to grade permit has been issued. The main
building permit is expected by the end of June
or early July. Completion date is March 2010.
Kogod Building Expansion – New
Lecture Hall: The Glass Fiber Reinforced
Concrete (GFRC) installation is about 50% complete.
Interior construction is progressing. The steam
line construction is expected to restart by June
11. The anticipated completion date is January
2009.
Mary Graydon Center (MGC) Exterior Improvements:
The project permit has been obtained. The temporary
ramp has been installed. Demolition is nearly
complete. Footings are expected to be poured this
week for the bridge. This phase of the renovation
project is scheduled for summer 2008. The canopy
will be constructed during winter break 2008.
The emergency exit paths from Butler Pavilion
has been reviewed and a missing exit signs will
be installed at the Butler 3rd floor lobby into
the MGC emergency stair.
Class of 2006 Gift: Orders have
been placed for the base construction, precast
caps and directory map box.
Katzen Museum Store: UA is working
with the College of Arts and Sciences to obtain
the Certificate of Occupancy.
Katzen – Condensation:
UA is working with an architectural firm to prepare
a solution to window condensation evident during
very cold winter weather. Other areas will be
monitored during the coming winter to assure correction
of all condensation issues.
Welcome Center Renovation: The
design has been developed with the Admissions
Office for improvements to the Centennial Hall
Welcome Center location and will be incorporated
into the summer construction project. Temporary
Welcome Center facilities have been constructed
in the music ensemble room at the Katzen Arts
Center. The Welcome Center will move back to Centennial
Hall in mid August 2008.
Bender Library Furniture and Remodeling:
The design has been developed with the Library
leadership and staff to replace selected furniture
and remodel and upgrade selected areas of the
Bender Library lower level. Chairs have been replaced
and pricing received for the remodeling efforts
which are expected to be complete by August. Furniture
deliveries may extend into the fall 2008 semester.
|