Project Status as of November 11, 2009

 

School of International Service (SIS):

Interior “rough-in” of building services is well underway and partition wall framing and wallboard installation is progressing.  Wiring for Tele/Data devices has begun. Exterior utilities are complete.  Roof installation is complete.  Completion date is May 2010.

 

Kogod Building Expansion – New Lecture Hall:  

Energy efficient LED light fixtures have been ordered and are expected to be delivered in January.  Benches are also needed and will be ordered soon.

 

Bender Library Furniture and Remodeling: 

The finishes for the reference desk and circulation desk are selected. Order placed.  A winter break delivery and installation is expected.

 

Exterior Signs: 

A project has begun to review the program and needs for exterior signs.  Analysis of the existing conditions and a review of needs have resumed.  Input from the Administrative Operations Project Team and other campus constituent groups will be needed.

 

Kreeger Building Remodeling:   

Construction will continue through early spring 2010.  Design for the relocation of the Audio-tech department is in progress.

 

Katzen Welcome Center "Admissions Green Room": 

The first phase of the relocation of the Admissions Green Room at the Katzen Arts Center is complete.  Update:

 

       Supplemental lighting has been installed in the garage

       Additional furniture being selected for the second floor of the rotunda and the upper terrace.

 

Clark/Roper Residence Conversion: 

Construction bids will be received in January 2010.  Construction will start in Roper upon the relocation of Economics to Kreeger.  Clark construction will begin when the SIS faculty and staff relocate to the new SIS Building. 

 

One Stop Center in Asbury: 

The 4200 Wisconsin build-out of a portion of the Registrar’s Office relocation in nearing completion. The move is expected to happen soon.  The One-Stop Center construction is expected to be complete by late February 2010.

 

University Center

Stairwell work will be done in MGC, Butler, and TDR form December 15 – January 8, 2010. The stairwells/lobby will be closed to pedestrian traffic during the project.  Work will include painting of walls and handrails, stair treads, flooring at landings and lobby (TDR). For access between MGC and Butler, patrons should use the covered bridge walkway.    Additionally, access to the Sports Center Parking Garage will be available through the elevators of Butler and Bender.

 