Projects

Project Status as of June 19, 2013

WAMU: Remodeling of 4401 Connecticut Avenue is well underway. A portion of the WAMU staff have relocated into office space at 4401. University Communications and Marketing staff have moved from Constitution Building on the Tenley Campus to 4401. Installation, testing and training on the broadcast equipment to be completed in September.

McKinley Remodeling - School of Communication: Sigal Construction is the contractor. Selective demolition is complete. Foundation work is complete. Steel columns and beams are complete. Utility rough-ins have started. Completion expected in December 2013.

Sports Center: Construction is underway for locker rooms remodeling. EYP is the architect/engineer. Davis Construction is the Construction Manager. Summer 2013 construction completion is planned.

East Campus: Design is underway. Little Diversified is the Architect. SKANSKA has been chosen as Construction Manager. Construction to start after commencement 2014. Completion by July 2016.

Nebraska Hall Addition: Grunley Construction is the General Contractor. Construction is underway. Interior rough-in is in progress. Completion is scheduled for August 2013.

Cassell Hall: Grunley Construction was selected as the Construction Manager for this project. Construction is underway. Interior work progressing. Utility work on-going. Completion is scheduled for early August 2013.

Washington College of Law at Tenley Campus: Construction has begun. Whiting -Turner selected as Construction Manager. Completion expected by July 2015.

3201 New Mexico Ave. North Plaza: Design for the repair of the waterproofing and replacement of the pavers is underway. Construction to take place in late Fall 2013.

MGC Terrace Seating Expansion: In design. The expansion of the seating area by relocating administrative office from the terrace level is expected to be complete this summer.

Ward First Floor Remodeling: In design. Work to be complete during the summer of 2013. Project consists of new furnishings and graphics with SPA branding to screen food vending area .

Asbury Third Floor Remodeling: In design. Construction Drawing to be complete in mid-July. Construction to be complete in September.

Other Projects in Planning: EQB second floor classroom partition, SIS remodeling for office space, Jacobs Fitness Center Office, Bender Library Planning and select furnishings, Brandywine Remodeling for SPExS and MGC 260 remodeling.